Getting the mains connection wrong is one of the most expensive mistakes you can make before a project starts. Too small and you're hiring a generator to cover the gap. Too large and you're paying standing charges on capacity you never use.

Start with peak demand, not average demand

Your Distribution Network Operator (DNO), the company responsible for electricity supply in your area, will size your connection based on your stated peak demand in kilovolt-amperes (kVA), which is the measure of total electrical load on a circuit. Most people underestimate this because they think about what's running most of the time, not what could all run at once. Walk through your plant schedule and ask: what's the worst-case moment? Typically it's when the tower crane is hoisting, the hoist is loaded, and welfare units are at full draw in the morning. That overlap is your peak.

Apply a diversity factor

Not everything runs at 100% simultaneously. A standard diversity factor for mixed construction loads is 0.5–0.7. Tower cranes and hoists are the exception. Treat them at full draw during overlap periods.

Standard connection sizes (UK, Three Phase and Neutral — TPN)

Current kVA Typical use
63A43 kVASmall welfare only
100A69 kVAWelfare + light loads
125A86 kVAMedium site, no crane
160A110 kVAMedium site with small crane
200A138 kVALarge site, single crane
315A218 kVAMulti-crane, heavy plant
400A277 kVAMaximum standard single connection

Anything above 400A TPN typically requires a substation — factor in 12–16 weeks lead time with the DNO.

When mains isn't enough

If your peak demand exceeds what the connection can supply, you have two options: upsize the connection (if lead time allows) or bridge the gap with battery storage. Battery storage is increasingly the smarter call: no fuel, no noise, and you only hire it for the weeks you actually need it.

The number most people get wrong

Mains capacity is constant. Site demand isn't. A 400A TPN connection handles your crane and hoist fine in weeks 1–20. But when the second crane arrives in week 21, you're over. That's the week you need battery storage. Not the whole project.